Renewable Energy Project

Woody biomass boiler No.2 Mikuni-cho, Sakai-shi, Fukui

鷹巣マルツ太陽光発電所
  • Brief overview

    Name Hutan(It means "forest" in Indon.)
    Silva (It means "forest" in Latin.)
    Address 4-4-8 Midorigaoka Mikuni-cho Sakai-shi Fukui
    (parking lot in Mikuni Kanko Hotel)
    Site area 67.83m²(Machine room)
    440.4m²(Slope for chip carrying vehicle)
    Fuel used 100 % cutting chips from unused wooden
    materials in Fukui (Japanese cedar)
    Silo capacity/type 70m³/semiunderground type
    Date of the first commercial operation December 14, 2015

Specifications

Equipment Manufactured by KWB(Austria):Multifire 120×2 units
Power 240kW(120kW×2 units)(catalog value)
Efficiency 92%(catalog value)
Chip amount in annual 350~400t/year(case of 8,000 hours operation in annual)
CO2 reduction in annual 350~400t/year(case of 8,000 hours operation in annual)
Remarks We installed the high performance boilers "Multifire" made in Austria where advanced in biomass technology.
There are only 4 units of "Multifire" in Japan. Ours are the 3rd and 4th units in Japan.
Those boilers could make the electricity, the frequency of ash handling pretty smaller.
We could reduce the construction cost for wood chip silo by using available high ground (height 1.6m) in parking lot.